top of page
STATE PROJECTS

PROJECTS IN 2022

Maryland Department of Planning

Project: BPM026275
Location: St. Leonard, MD: Jefferson Patterson Park, Grading around Breckinridge Classroom

Project Description:

Projected Started

2022

Projected Completed

2022

PROJECTS IN 2021

Maryland Department of Public Safety and Correctional Services

Project: BPM025509
Location: Sykesville, MD: Driver Training Facility

Project Description:

Repair four (4) sinkholes that began forming in front of four (4) At Grade Inlet structures, the sinkholes formed due to an array of issues including failed joints inside the Reinforced Concrete Pipes (RCP) draining into two of the inlets, on these inlets the RCP was excavated to expose the separated joints. The joints were realigned, patched and backfilled. The third inlet had several missing bricks around the frame and cover, the outside of the inlet was excavated the missing bricks replaced and the interior of the inlet was parged. The fourth inlet had a 6" drain pipe connecting into the side of the inlet, the outside wall was excavated down to the drain pipe and no additional drain pipe was uncovered. This area was backfilled and the connection point was filled, the asphalt was replaced at each of the inlets and the sediment and debris inside the inlets were also removed.  

Projected Started

November 19th, 2021

Projected Completed

November 22nd, 2021

PROJECTS IN 2020

Maryland Department of General Services

Project: BPM020098
Location: Prince Frederick, MD: State Police Barracks "B"

Project Description:

Repair sinkhole that formed in front of the curb inlet structure, the sinkhole formed due to the interior wall of the curb inlet collapsing and multiple failed joints inside the 15" Reinforced Concrete Pipe (RCP) that drained into this inlet. The front interior wall and curb were removed and all of the sediment was removed from within the inlet, the front wall and curb were replaced. Multiple joints along the connection between the two inlets were compromised, these failed joints were allowing sediment to enter the pipe and forming other sinkholes in the parking lot. The joints were excavated and repaired and multiple sections of the pipe were adjusted for proper drainage. A change order was issued once this portion of the work was completed, while removing sediment from the inlet a 12" PVC drainage pipe was uncovered. This 12" PVC pipe served as an initial outflow that drained into a Bio-Retention facility down stream. The outflow pipe was jet-vacuumed and during the next rain event the water drained properly from the inlet.

Projected Started

August 10th, 2020

Change Order Issued

August 24th, 2020

Change Order Completed

August 25th, 2020

Projected Completed

August 25th, 2020

bottom of page